SP-SFIF Regional Activities of the Strategic Partnership for a Sustainable Fisheries Investment Fund in the Large Marine Ecosystems of Sub Saharan Africa - Tranche 1

Project Summary

The objectives of this Grant to support the Regional Activities of the Strategic Partnership are to: -Strengthen regional coordination in order to ensure complementarity among country-level and regional projects, in particular in respect to management of trans-boundary resources;-Promote learning and information exchange at the regional level to ensure that the lessons from successes and failures of country and LME level investments are adequately disseminated; and-Encourage direct financial support in the SSA countries for the necessary governance (i.e. policy, legal, and institutional) reforms and sector adjustments to manage their fisheries sustainably in a way that ensures a distribution of benefits that will contribute to poverty reduction and food security; -Assist individual coastal countries to build the capacity to participate in the ongoing GEF-led Large Marine Ecosystem (LME) projects and regional fisheries bodies (RFBs) as well as collaborate through these initiatives to implement management measures for the marine ecosystems and the trans-boundary fisheries resources and/or fishing fleets that would be more appropriate at the sub-regional scale (e.g. sub-regional monitoring, control and surveillance systems, management of fishing capacity, sub-regional research initiatives, networks of marine protected areas (MPAs), etc.).

Project Details

GEF Project ID
3271
Project Type
Medium-size Project
Status
Completed
Country
Regional
Region
Focal Areas
Funding Source
GEF Trust Fund
Implementing Agencies
The World Bank
Executing Agencies
African Union, United Nations Food & Agriculture Organization (FAO), World Wildlife Fund (WWF)
GEF Period:
GEF - 3
Approval Fiscal Year:
2007

Financials

Project Preparation Grant Amount
0 USD
GEF Project Grant
1,000,000 USD
Co-financing Total
330,000 USD
GEF Agency Fees
90,000 USD
Total Cost 1,330,000.00 USD

Project Timeline

Received by GEF
25 Oct 2006
Concept Approved
16 May 2007
Project Approved for Implementation
15 May 2007
Project closed
22 Nov 2011