Solid Waste Management and Landfill Gas Recovery
Project Summary
To harness methane for electricity production that otherwise would have been emitted to the atmosphere, as well as to assist the management of solid waste around Riga, the project will remediate the existing Getlini landfill in Riga, install an advanced energy-cell technology for enhanced degradation of biodegradable waste, and collect landfill gas and use it for power generation. In addition, the project will establish a sorting line for separation of recyclable materials, and provide technical assistance for the overall system.
Project Details
| GEF Project ID | 123 |
| Project Type | Full-size Project |
| Status | Completed |
| Country | Latvia |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | The World Bank |
| Executing Agencies | World Bank |
| GEF Period: | GEF - 1 |
| Approval Fiscal Year: | 1997 |
Project Documents
Financials
| Project Preparation Grant Amount | 0 USD |
| GEF Project Grant | 5,120,000 USD |
| Co-financing Total | 20,090,000 USD |
| GEF Agency Fees | 0 USD |
| Total Cost | 25,210,000.00 USD |
Project Timeline
Received by GEF
Concept Approved
01 Mar 1997
Project Approved for Implementation
03 Feb 1998
Project closed
12 Sep 2005