Rural Electrification and Renewable Energy Development

Project Summary

The Project development objectives are : (i) To create a comprehensive Rural Electrification Strategy and an enabling environment for exploiting renewable energy; and (ii) To implement appropriate institutional set-up and regulatory framework for rural electrification and renewable energy development in a sustained manner.

Project Details

GEF Project ID
2649
Project Type
Medium-size Project
Status
Completed
Country
Yemen
Region
Focal Areas
Funding Source
GEF Trust Fund
Implementing Agencies
The World Bank
Executing Agencies
Ministry of Electricity
GEF Period:
GEF - 3
Approval Fiscal Year:
2005

Financials

Project Preparation Grant Amount
0 USD
GEF Project Grant
999,232 USD
Co-financing Total
0 USD
GEF Agency Fees
0 USD
Total Cost 999,232.00 USD

Project Timeline

Received by GEF
24 Nov 2004
Concept Approved
22 Dec 2004
Project Approved for Implementation
21 Dec 2004
Project closed
20 Nov 2008