Promoting the Use of Renewable Energy Resources for Local Energy Supply

Project Summary

Promotes investments in small hydro power based on IPP/PPA frameworks and also promotes geothermal energy for municipal hot water supplies based on municipal government investment and operation. Project $12.85 m.; GEF $4.3 m.

Project Details

GEF Project ID
1137
Project Type
Full-size Project
Status
Completed
Country
Georgia
Region
Focal Areas
Funding Source
GEF Trust Fund
Implementing Agencies
United Nations Development Programme
Executing Agencies
Government of Georgia
GEF Period:
GEF - 3
Approval Fiscal Year:
2003

Financials

Project Preparation Grant Amount
211,500 USD
GEF Project Grant
4,300,000 USD
Co-financing Total
9,330,000 USD
GEF Agency Fees
382,000 USD
Total Cost 13,841,500.00 USD

Project Timeline

Received by GEF
Preparation Grant Approved
23 Jul 1998
Concept Approved
01 Oct 2002
Project Approved for Implementation
10 Feb 2004
Project closed
24 Jun 2014