Promoting Sustainable Energy Access for Rural Communities in South-Eastern Angola
Project Summary
To catalyse investments in decentralised renewable Energy systems to expand energy access for Base-of-the-pyramid consumers and to reduce GHG emissions
Project Details
| GEF Project ID | 9810 |
| Project Type | Full-size Project |
| Status | Concept Approved |
| Country | Angola |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | United Nations Development Programme |
| Executing Agencies | Ministry of Culture, Tourism and Environment |
| GEF Period: | GEF - 6 |
| Approval Fiscal Year: | 2018 |
Project Documents
- CEO Endorsement/Approval Review Sheet Document
- CEO Endorsement/Approval Review Sheet Document
- PIMS 5989 - Rural Energy Access in Angola CEO ER - 23 September 2019
- FSP CEO endorsement document
- PIMS 5989 - Rural Energy Access in South Eastern Angola - ProDoc - revsied April 20
- PIMS 5989 Co-financing Letters Aug 13
- PIMS 5989 - Financial Analysis - Annex SA7
- PIMS 5989 - GHG Emission Reduction Calculations - Annex SA6
- PIMS 5989 - Access to Finance - Baseline assessment - Annex SA5
- PIMS 5989 - Technology Baseline Assessment - Annex SA4
- PIMS 5989 - SHS DREI Angola - v3 - Annex SA3
- PIMS - 5989 - Theory of Change - v1 - Annex SA2
- PIMS 5989 - Stakeholder Engagements - Baseline Assesments - Annex SA1
- PIMS 5989 Co-financing Letters
- PIMS 5989 - Rural Energy Access in South Eastern Angola - ProDoc - May 28 2019
- PIMS 5989 - Rural Energy Access in Angola CEO ER - May 28 2019-1
- PIMS 5989 - OFP letter for DPC
- PIMS 5989 - GEF7 Core Indicators - CEO ER - Annex E-1
- PIMS 5989 - GEF Taxonomy Worksheet - CEO ER - Annex F-1
- PIMS 5989 - Co-finance letter
- PIMS 5989 - Annex G - Gender Analysis and Action Plan
- PIMS 5989 - Annex F - Stakeholder Engagement Plan
- 5885 Annex H UNDP Risk Log
- PIMS 5989 - Annex E - UNDP SESP
- 5885 Annex A Multi Year Work Plan
- STAP Review (PDF)
- Review Sheet (PDF)
- PIF Document for WPI (Revised)
Financials
| Project Preparation Grant Amount | 150,000 USD |
| GEF Project Grant | 3,540,468 USD |
| Co-financing Total | 21,000,000 USD |
| GEF Agency Fees | 336,344 USD |
| Total Cost | 24,690,468.00 USD |
Project Timeline
Received by GEF
22 Mar 2017
Preparation Grant Approved
30 Oct 2017
Concept Approved
01 Nov 2017
Project Approved for Implementation
Project closed