Harmonization of National Action Plan to combat desertification in Armenia and Preparation of National Report
Project Summary
1. The review of “National Action Plan of UNCCD in Armenia” proceeds from UNCCD 10 year strategic plan which established the scope of strengthening activities for the implementation of the Convention(2008-2018). It was established during the 8th session of the COP by the decision 3/COP.8 . Besides NAP was developed about 10 years ago on the basis of 1990-1995 existing data.2. The elaboration of 2012 National Report on the implementation of UNCCD in Armenia proceeds from the requirements of the 26 article of UNCCD, as well as from the decisions 13/COP.9, 3/COP.10 of the Conference of Parties.
Project Details
| GEF Project ID | 4977 |
| Project Type | Enabling Activity |
| Status | Project Approved |
| Country | Armenia |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | GEF Secretariat |
| Executing Agencies | “Environmental project implementation unit” State Agency under the Ministry of Nature Protection of RA |
| GEF Period: | GEF - 5 |
| Approval Fiscal Year: | 2012 |
Project Documents
Sorry, no documents available
Financials
| Project Preparation Grant Amount | 0 USD |
| GEF Project Grant | 150,000 USD |
| Co-financing Total | 40,000 USD |
| GEF Agency Fees | 0 USD |
| Total Cost | 190,000.00 USD |
Project Timeline
Received by GEF
24 Apr 2012
Concept Approved
08 May 2012
Project Approved for Implementation
07 May 2012
Project closed