Expedited Financing of Climate Change Enabling Activities Part II, Expedited Financing for (interim) Measures for Capacity Building in Priority Areas
Project Summary
The project is being implemented as an interim activity between the Initial and the Second Communications. Hence it is intended to complement activities of Phase 1 project, related to the Initial Communication, while at the same time forming basis for initiation of the Second National Communication of Cote d'Ivoire to the UNFCCC.
Project Details
| GEF Project ID | 1467 |
| Project Type | Enabling Activity |
| Status | Completed |
| Country | Cote d'Ivoire |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | United Nations Environment Programme |
| Executing Agencies | Ministere de l Environnement et du Cadre de Vie |
| GEF Period: | GEF - 2 |
| Approval Fiscal Year: | 2002 |
Project Documents
Financials
| Project Preparation Grant Amount | 0 USD |
| GEF Project Grant | 100,000 USD |
| Co-financing Total | 0 USD |
| GEF Agency Fees | 0 USD |
| Total Cost | 100,000.00 USD |
Project Timeline
Received by GEF
07 Sep 2001
Concept Approved
26 Oct 2001
Project Approved for Implementation
25 Oct 2001
Project closed
11 Oct 2010