Enabling activities to facilitate early action on the implementation of the Stockholm Convention on Persistent Organic Pollutants (POPs) in Rwanda
Project Summary
The overall objective of the proposed Enabling Activities (EA) is to strengthen national capacity and capability to prepare a National Implementation Plan (NIP) for the management of POPs. This plan will provide a basic and essential level of information to enable policy and strategic decisions to be made and identify priority activities that Rwanda should undertake in order to meet the requirements of the Stockholm Convention. It will be endorsed by all stakeholders before transmission to the Conference of Parties (COP).
Project Details
| GEF Project ID | 1974 |
| Project Type | Enabling Activity |
| Status | Completed |
| Country | Rwanda |
| Region | |
| Focal Areas | |
| Funding Source | GEF Trust Fund |
| Implementing Agencies | United Nations Industrial Development Organization |
| Executing Agencies | Directorate of Environment Protection, Ministry of Land, Human Resettlement and Environmental Protection |
| GEF Period: | GEF - 3 |
| Approval Fiscal Year: | 2003 |
Project Documents
Financials
| Project Preparation Grant Amount | 0 USD |
| GEF Project Grant | 371,000 USD |
| Co-financing Total | 0 USD |
| GEF Agency Fees | 0 USD |
| Total Cost | 371,000.00 USD |
Project Timeline
Received by GEF
18 Dec 2002
Concept Approved
08 Jan 2003
Project Approved for Implementation
07 Jan 2003
Project closed
31 Dec 2012