Barriers and Best Practices in Integrated Management of Mountain Ecosystems

Project Summary

The overall objective of the project is to assist developing countries to promote and enhance the protection and sustainable development of the mountains and their resources globally, as a contribution to the International Year of Mountains, WSSD and BGMS. Through collaboration among GEF implementing agencies and other partners this MSP will identify best practice in GEF and non-GEF projects dealing with biodiversity, climate change, and international waters in the context of integrated management of mountain ecosystems. Common obstacles to success and lessons learned from recent experiences will be highlighted.

Project Details

GEF Project ID
1328
Project Type
Medium-size Project
Status
Completed
Country
Global
Region
Focal Areas
Funding Source
GEF Trust Fund
Implementing Agencies
United Nations Environment Programme
Executing Agencies
UNEP-WCMC
GEF Period:
GEF - 2
Approval Fiscal Year:
2002

Financials

Project Preparation Grant Amount
25,000 USD
GEF Project Grant
900,000 USD
Co-financing Total
1,199,000 USD
GEF Agency Fees
146,000 USD
Total Cost 2,124,000.00 USD

Project Timeline

Received by GEF
27 Jun 2001
Preparation Grant Approved
25 Jul 2001
Concept Approved
07 Mar 2002
Project Approved for Implementation
06 Mar 2002
Project closed
09 Jun 2005